As part of the M62 Junction 8 Improvement Scheme, night time works are planned to be carried out from Monday 13th February up to and including Thursday 2nd March 2017 between the hours of 20:30 and 05:30.

Please find below details of the works or download a plan below for reference:

Monday 13th February
Burtonwood Road North – Southbound carriageway lane closures for ducting and drainage crossings

Tuesday 14th February
Burtonwood Road North – Southbound carriageway lane closures for ducting and drainage crossings

Wednesday 15th February
Burtonwood Road North – Southbound carriageway lane closures for ducting and drainage crossings

Thursday 16th February
Jct 8 Gyratory – Southbound carriageway duct crossings

Friday 17th February
Jct 8 Gyratory – Southbound carriageway duct crossings

Monday 20th February
Eastbound off slip lane closure for duct crossings

Tuesday 21st February
Eastbound off slip lane closure for duct crossings

Wednesday 22nd February
Jct 8 Gyratory – Westbound (top of Burtonwood Road) for duct crossings

Thursday 23rd February
Jct 8 Gyratory – Westbound (top of Burtonwood Road) for duct crossings

Friday 24th February
Westbound off slip lane closures for duct crossings

Monday 27th February
Westbound off slip lane closures for duct crossings

Tuesday 28th February
Skyline Drive Full Closure (East & West) for drainage connection to Manhole

Wednesday 1st March
Skyline Drive Full Closure (East & West) for drainage connection to Manhole & Westbound On Slip Full Closure

Thursday 2nd March
Skyline Drive Full Closure (East & West) for drainage connection to Manhole & Westbound On Slip Full Closure (Contingency)